The date change, in depth
What does moving a show date do to your crew and budget?
In ShowOps.AI, confirming a change to the production timeline produces a report: which crew bookings move, the change in staffing cost (day rates and per diem included), and the budget lines linked to those bookings. The crew date changes become one suggestion that a producer approves or rejects, and an approved change can be undone.
Why it matters
The usual way is to edit the schedule, then find the roster tab, then the budget tab, then call the crew. The cost hides in the gaps: an extra day on a booking, per diem for a night nobody planned, a budget line nobody updated.
How it works, step by step
- Crew bookings are anchored to milestones on the production timeline, so the report knows which bookings a moved milestone affects.
- Timeline edits save as you work. Crew dates and the budget do not change until you confirm.
- An explicit confirm runs the report. The first confirm on a project records the starting timeline; reports start from the second.
- The report covers staffing and budget together.
- The crew date changes become one suggestion to approve or reject. An approved change can be undone.
- Every confirmed version of the timeline is kept.
Worked example
Illustrative example, not customer data.
The tech rehearsal moves one day earlier. Two crew bookings anchored to it now start a day sooner.
| Crew booking | Days | Staffing cost change | Linked budget line |
|---|
| A1 audio engineer | 3 to 4 | +$725 (day rate $650, per diem $75) | Labor: audio |
|---|
| LED technician | 2 to 3 | +$625 (day rate $550, per diem $75) | Labor: video |
|---|
Total staffing cost change: +$1,350
What it does not do
- It does not re-staff the show or pick replacement crew.
- It does not move vendor bookings.
- A crew booking must be anchored to a timeline milestone to be moved and priced.
- Budget impact covers crew bookings linked to a budget line. The report lists the unlinked ones instead of counting them as zero.
- Trying out a timeline change without confirming it has no editor yet.
No AI involved
The date-change calculation is deterministic. AI is not used to price the change.